Transport Infrastructure news in Jalan Magazine
-
Jalan Sultan Azlan Shah closed 322 days for Mutiara LRT works
MRT Corp announced that Jalan Sultan Azlan Shah in George Town will have a 322-day traffic diversion from Sept 12, 2026 to July 31, 2027 for piling and structural works on the Mutiara Line LRT. Jalan Magazine will also be partially closed from 10pm on Sept 14 to 5am on Oct 5 for road widening and utility relocation.
-
Penang to auction Tanjung Pinang land to fund Ayer Itam bypass project
The Penang government will auction a 2.42-hectare freehold plot in Tanjung Pinang on October 7 to help contractor Consortium Zenith Construction secure cash flow for the Ayer Itam-Tun Dr Lim Chong Eu Expressway bypass. The project is 92.46% complete and targeted for completion by April 2027.